7. Construction

Demonstrate your contribution to construction, including sequence, temporary conditions, tolerances, access and plant.

In this guide
LEARNING GUIDE

Use this material to examine your own work. Confirm current requirements, forms and dates with IStructE before applying.

The minimum standard is Experience for both Incorporated-Member and Chartered Member.

What strong and weak evidence look like

Look for

  • A design change you made because of how it would be built.
  • A temporary condition you identified that governed the permanent design.
  • A site problem you were called to and resolved, with what you decided.
  • A construction sequence you thought through, including the stage that was most vulnerable.
  • Evidence of tolerance, setting out or fit being designed for rather than discovered.

Watch for

  • Site visits with photographs, and no decision attached.
  • "I attended site meetings."
  • A design with no evidence that anyone considered how it would be erected.
  • Treating buildability as the contractor's problem.

Portfolio items that tend to work here

Suggestions, not a required list. What matters is that the item is yours, that it is annotated, and that it demonstrates the standard rather than the subject.

Questions to ask yourself

  1. What is the worst stage during construction?

    The temporary condition governs far more often than candidates expect.

  2. What did I change because of how it would be built?

    That change is the evidence. Awareness of buildability is not.

  3. Have I been on site for my own design?

    Engineers working mainly in a design office may need further opportunities to demonstrate construction experience.

The same objective, in different kinds of work

SettingWhat the evidence tends to look like
DesignerChanging a detail so it could be built without working at height, and recording what remained.
Site engineerSequencing a pour or a lift, and holding the line when the programme pushed back.
Temporary worksDesigning or checking a propping scheme, and setting what had to be verified before load was applied.

Illustrative. The objectives are written to be met in a range of ways by anyone practising as a structural engineer.

How reviewers tend to approach this objective

  • Asking how your structure was erected, stage by stage.
  • Asking what the crane could and could not reach.
  • Asking what went wrong on site and what you did.
  • Asking about tolerances and what happens when they accumulate.

There is a bank of original practice questions in the interview question bank, filterable by objective and by grade.

Official sources